Three Waters

St Vincent Street Stormwater Upgrade Stages 2 & 3

Client:
Nelson City Council (NCC)
Date:
2025 - 2026

The second and third stages of a major stormwater upgrade in central Nelson, to improve resilience of this area to flooding from a 1:50 to a 1:100-year event and provide improved security for the city’s road network.

As part of the Principal’s team during the ECI phase, we identified and reviewed procurement options; peer reviewed and revised the procurement documentation for the ECI to reflect project risk; collaborated with the ECI contractor around constructability methodology, innovation and price; and were part of the tender evaluation team. Post-award, we were retained as Principal’s Advisor to review commercial matters and variations.

Services: ECI procurement document review & revision | Design & constructability review | Tender evaluation | Physical works price reviews | Principal’s Advisor (commercial & methodology)

Team: Paul Duffy | Matt Armstrong

Get in touch with us

LET'S MAKE SOMETHING GREAT TOGETHER